Elves Special Needs Society Building Addition
Project Description
Canbian has been retained as the General Contractor for the Elves Society Building Addition and Renovations. Construction started in August 2018 with the demolition of a portion of the existing building to make way for the new addition. The existing building foundations needed to be underpinned and supported before construction of the new basement could commence. The new addition is made of reinforced concrete footings and concrete walls, structure steel columns, beams, OWSJ and metal floor and roof deck. Completion is slated for end of August 2019.
Specifications
LocationEdmonton, AB
Duration12 months
Size11,000 square feet
TypeInstitutional / Tender